Amazon’s (NASDAQ:AMZN) plan to build a data center powered by a Pennsylvania nuclear power plant has not changed, even as the ...
Nuclear plant owner Talen Energy Corp. says an initial 300 MW of data center development can proceed despite feds' rejection of grid link agreement to its Susquehanna facility in Pennsylvania's ...
Chairman Willie Phillips dissented from the decision on the “first of its kind” co-location proposal, saying it could harm ...
The company’s “foot is on the accelerator” to close data center deals as it works to restart Three Mile Island Unit 1 by 2027 ...
The Federal Energy Regulatory Commission (FERC) rejected an effort Friday to allow an Amazon data center to tap into ...
Nuclear-power stocks fell after regulators voted against a deal between Amazon and Talen Energy.The deal would permit a Talen ...
The commission agreed with opponents of the proposal, citing concerns about grid reliability and cost fairness.
The Amazon data center is located close to Talen's Susquehanna nuclear power plant in Pennsylvania, as previously reported. The amended interconnection deal would have supplied more power directly ...
The proposal aimed to revise an ISA involving PJM, the regional grid operator, Susquehanna Nuclear, which owns the power plant, and transmission owner PPL Corp. The amendment would boost the data ...
The Federal Energy Regulatory Commission (FERC) has rejected an amended interconnection agreement that would have supported ...
The denial of a power agreement tied to Amazon Web Services' nuclear data center campus could slow a potential wave of ...
Shares of Talen Energy (TLN) are under pressure on Monday after the Federal Energy Regulatory Commission, or FERC, rejected an amended ...